RSG completes foundation works on Burj Sabah

October 16, 2017

undefinedRSG International has successfully completed the reinforced concrete raft foundation works on its project, Burj Sabah. 

The casting work was completed in 24 hours by a team of 140 on-site crew members.

Al Asri Engineering Consultant and Team Engineering Enterprises Ltd. were part of the construction team.

The foundation used 3,400 cubic metres of concrete and 640 tonnes of steel.

The 19-storey building is located Jumeirah Village Circle (JVC) and will house studio apartments as well as one and two-bedroom apartments.

The project is expected to be completed in February 2019.

Other projects by the firm include Qasr Sabah in Dubai Production City, which was completed 86 days ahead of its projected date. 